Prep Phase

 

Construction Hotline Phone Number 715.346.5005

back to home page

We are currently in our prep-phase of construction. During this phase we are completing our internal building remodeling and relocation projects to make room for our Emergency Room, ambulatory surgery and other outpatient areas construction project. Demolition and construction of these areas will begin in May 2014.

June 25. 2014

Oxygen Tank Relocation Complete
The oxygen tank relocation project is complete and the upper parking ramp is once again open for associate parking. See photos.

Parking
Please remember that parking for patients remains a top priority, so watch for periodic notices about shuttle service, entrance and parking changes throughout the construction project. For your convenience, bike racks are available on the north and west side of the building. There is also a motorcycle/moped parking area now available in the north parking lot. We ask that you continue to be respectful and follow all parking regulations when parking on the street as our neighbors have expressed concerns.

Congratulations to Heather Kawlewski, Coding, who was selected as the May winner for the “Doing My Part for Parking Program.” Heather has been walking to work over 50% of her scheduled shifts. Remember you can enter to win each month by biking, walking, or ride sharing to work. Thank you to all who have been doing their part to make sure parking is available for our patients, and for everyone’s continued patience and cooperation.

New CT scanner: The noise coming from Diagnostic Imaging is from suite construction to house the new Siemens, SOMATOM® Definition Flash 128-slice dual source, CT scanner. Watch for more details about this suite opening in late July.

June 9, 2014

Ministry Saint Michael’s Hospital Construction Project: Oxygen Tank Immediate Notice Temporary Tie-In

The move to the temporary oxygen tank is complete. Oxygen will be released from the existing tank to ready for its removal tomorrow. This may result in smoke and noise during the 30-40 minute process. This is normal procedure and should not be cause for alarm.
 

May 2014

Surgical Services Entrance Moves to Front of Hospital During Construction:

We would like to take this opportunity to thank you for choosing Ministry Health Care and Ministry Saint Michael’s Hospital for your surgical care. We strive to give excellent care to every patient and customer. When you arrive, please park in the Main Parking Lot (entrance off Stanley Street refer to location map), enter the hospital through the Main Entrance revolving door and check in at the Information Desk. Please be aware that the Main Doors open at 5:30 a.m. Monday through Friday. Staff at the information desk will provide you with a map or an escort to your registration location. Please note you will also be discharged from the Main Entrance. Your surgery start time is an estimated time. Occasionally surgeries may be delayed for emergencies.We appreciate your understanding if your procedure is delayed. We will make every effort to keep you informed while you wait. Download our day of surgery letter for more information.

Parking Update:

We are excited to announce that ED/ASC construction will soon be underway. The next step is the relocation of the oxygen tank – please watch for information on specific dates and times. As with any major construction/remodeling projects, we will be faced with some inconveniences. This project will necessitate some parking and shuttle bus service adjustments.

Parking adjustments to note:

Patients come first. Our first and foremost focus is to ensure that our patients and guests have convenient and adequate parking. 

Associate safety. Every effort has been made to provide a safe parking environment for associates. Parking ramp gates will be down 24/7 coinciding with the beginning of the oxygen tank relocation. Associate name badges are required (and appropriate authorization) to access the gates.

Parking decals. Required for associates parking at  900 Illinois Ave & 2501Main Street building.

Shuttle bus. The shuttle bus drop-off/pick-up location moves from the employee entrance to the city bus shelter on Fremont Ave.

Street parking. Please respect our neighbors if you choose street parking.  Previous complaints included blocked driveways, tobacco and trash littering. Associates are responsible for any tickets issued by the Stevens Point Police Department. 

Emergency and Urgent Care
Ministry Saint Michael’s Hospital Emergency and Urgent Care will remain open during construction.  Plover Urgent Care is also available.
 

March 2014

PARKING UPDATES DURING CONSTRUCTION

We are excited to announce that ED/ASC construction will soon be underway. The next step is the relocation of the oxygen tank – please watch for information on specific dates and times. As with any major construction/remodeling projects, we will be faced with some inconveniences. This project will necessitate some parking adjustments.

Parking adjustments to note:
Patients come first. Our first and foremost focus is to ensure that our patients and guests have convenient and adequate parking. 

Street parking. Please respect our neighbors if you choose street parking. Previous complaints included blocked driveways, tobacco and trash littering. Associates are responsible for any tickets issued by the Stevens Point Police Department. 

CUSTOMER SERVICE CHANGES

Due to the upcoming renovation project Ministry Saint Michael’s Hospital, the Customer Service Department will be moving to an external location effective April 27, 2014.  While no longer on-site at the hospital, our customer service associates are dedicated to assist you and are committed to offering quality patient -friendly customer service. 

Please call us Monday-Friday: 7:30 a.m. - 4:30 p.m. at 715.346.5170
Payments may be mailed to: PO Box 3218, Milwaukee, WI 53201-3218.
Payments may also be made online at: ministryhealth.org. Your continued patience and cooperation is most appreciated.

 

February 2014

We are pleased to announce that construction of our new Emergency Department (ED) and renovation of our Ambulatory Surgery Center (ASC) will soon be underway. Ministry Saint Michael’s Emergency Department is the busiest in the Ministry system and we are looking forward to the changes to the new facility that will allow us better serve our patients.

Equipment will arrive onsite to make way for demolition in late March (weather dependent). During this phase, demolition of a portion of the south and east side of the building will occur as well as relocation of the oxygen tank.

Emergency and Urgent Care
Ministry Saint Michael’s Hospital Emergency and Urgent Care will remain open during construction. Plover Urgent Care is also available. 

 

 

December 2013

Our volunteers are moved in and already making the front lobby space their own. Sherri Vetter, Volunteer Coordinator, reports that all is well and volunteers look forward to continuing to offer the great service from their new office. Did you know that on average, there are over 20 volunteers that rotate through the volunteer office daily?  The new space will give the volunteers greater exposure and access.

 

 

November 2013

We are currently in our prep-phase of construction. During this phase we are completing our internal building remodeling and relocation projects to make room for our Emergency Room, ambulatory surgery and other outpatient areas construction project. Demolition and construction of these areas will begin in March 2014

MILESTONE DATES

October 17, 2013  Neighborhood Meeting
October 22, 2013  Ground Breaking Ceremony
October 22, 2013  Initial Internal Construction Projects begin
In progress:        

  • Telecom relocates to front lobby
  • Transformer relocation on east side of hospital building
  • Oxygen tank moves to west side of parking ramp entrance
  • Line for utilities moves to back drive

2014 March - Demolition and construction start
2015 March - New Emergency Department opens
2015 December - Remodeling Completed

 

 
 